Amtrak and NJ TRANSIT joined Gov. Phil Murphy today to share the progress on their joint inspection, maintenance, and improvement program for Amtrak’s Northeast Corridor (NEC) infrastructure and NJ TRANSIT’s trains. Today’s meeting follows a June 27th meeting led by the governor to determine a joint action plan designed to address major service disruptions that occurred throughout the summer.
After issuing a report in August, which included details of joint efforts and progress to date, Amtrak and NJ TRANSIT released a new progress report today and discussed the recently-awarded grants for nearly $300 million in federal funding to modernize critical rail infrastructure in New Jersey.
“With today’s meeting, we are proud to announce that Amtrak has now completed its inspection of all 240 miles of catenary overhead wire systems between Trenton and New York City. And while the fundamental challenge facing our mass transit system continues to be aging infrastructure, we believe that these completed repairs, and the infrastructure investments to come, will make sure New Jerseyans have an easier time getting where they need to go when they need to get there,” Murphy said.
“Our partnership with NJ TRANSIT and joint commitment to Governor Murphy to ensure that our collective customers have safe and reliable train service is achieving results,” said Amtrak CEO Stephen Gardner. “Amtrak and NJ TRANSIT will continue to conduct inspections, make short-term repairs and seek more funding to fully modernize all aspects of our infrastructure over the long term, including our electric traction system, catenary, signals, switches and more.”
“While we are pleased with the progress that has improved reliability for tens of thousands of NJ TRANSIT rail customers, our joint efforts will continue,” said NJ TRANSIT President & CEO Kevin S. Corbett. “It’s essential that we sustain the same level of attention we have demonstrated over the past five months. In addition to the work we are doing to add fiberglass protectors on our pantographs to protect them from impact damage on the NEC catenary, NJ TRANSIT will continue to support Amtrak’s efforts to accelerate the work to upgrade the most vulnerable infrastructure along the NEC.”
The execution of the joint action plan followed several major service disruptions in May and June, together with a variety of smaller incidents that reduced service reliability on the NEC between Trenton and New York City. Following June’s public meeting with the governor, Amtrak and NJ TRANSIT outlined immediate actions, investigations, inspections and repairs that both companies undertook together to address these issues.
Over the course of the past five months, Amtrak and NJ TRANSIT made the following improvements executing on their joint plan:
In addition to those improvements, Amtrak recently received nearly $300 million in grants, applied for with NJ TRANSIT support and matching funds, from the FRA for several projects that will modernize the area’s infrastructure. This includes funding to advance further planning, development, or construction activities as follows: